Main Street Project (Main Street Implementation Plan)
Purpose and Background
The Main Street project is a continuation of the previous Downtown Neighborhood District Planning effort that resulted in a long-range concept vision for Mammoth's Main Street and Downtown area, called the Downtown Concept for Main Street.
The Main Street Project will result in a detailed phasing and implementation plan that comprehensively addresses both the physical and financial feasibility of making the Downtown Concept for Main Street a reality.
The Main Street Project is fully grant-funded through a California Department of Transportation Community-Based Transportation Planning grant. The Project is also being completed in conjunction with the Town's comprehensive Zoning Code Update.
Final Main Street Plan
The Town Council accepted the Main Street Plan on February 19, 2014.
Draft Main Street Plan
The Draft Main Street Plan was developed after a thorough public engagement process, which included discussions with Main Street property and business owners, community members, and interested stakeholders. The draft document was presented to the Town Council and the Planning and Economic Development Commission at a joint meeting on October 16, 2013. The public comment period closed on November 15, 2013.
Previous Meetings and Materials
October 16, 2013 Draft Main Street Plan
- Draft Main Street Plan (PDF)
- Draft Main Street Plan Attachments (PDF)
- Framework Concept Poster (PDF)
- Public Comment Form (PDF)
Community Workshops and Openhouses, April 2nd through 4th, 2013
In early April, the Town held a series of public workshops, open house events, and meetings with stakeholders to discuss strategic, phased solutions aimed at acheiving the Main Street vision. The events were a success; information and materials from the workshops, open houses, and meetings is provided below:
- Existing Utilities (PDF)
- Existing Land Use Plan (PDF)
- Existing Zoning (PDF)
- Aerial Photo Including Previously Approved Projects (PDF)
Final Presentation April 4, 2013
- PowerPoint Presentation - Final Summary (PDF)
- Concept Final Street Design with Example Phasing of New Development (PDF)
Planning Commission Workshop (kick-off), February 12, 2013
Downtown Working Group
The Downtown Working Group consists of a small group of stakeholders and Planning and Economic Development Commissioners tasked with assisting staff with the Main Street Project and update to the Town's Commercial Zoning Chapter of the Zoning Code Update.
The Downtown Working Group meetings are public meetings. Agendas, meeting notes, and group materials can be found on the Downtown Working Group page.